The Installation of various Pre Cast Concrete abutment extension units, cill beams, TY beams and edge / parapet units to create the all new widened bridge deck at Road Over Bridge 13, Central Drive, Walsall. Loads varying in weight from 3.50te for the TY beams, 33.10te for the abutment extensions and 48.00te for the edge beams.
Crane: Liebherr LTM1500-8.1 – 165te C/W & 47.3m TY3 supplied by Baldwins Crane Hire
Other Equipment:
Pneumatic Chain Hoists, Endless Slings, Master Links, Shackles, Manual Chain Blocks and various Chains Slings