Where was the generator removal and reinstallation project located?
The generator removal and reinstallation project was located in Central London.
The Challenge
An 18.0te Generator too heavy to remove as a completed unit located on the 17th floor of a fully operational building, adjacent to a live helipad. The project involved the specialist removal and reinstallation of a backup Generator from the 17th-floor plant room — a high-risk lift and shift operation with tight access, significant height, and complex logistics. Following a successful removal in the summer of 2024, the generator underwent refurbishment and testing, before the team returned to complete the final stage of the project: the lift and reinstallation. However, we could not reply on the weather despite clear skies and good visibility, high winds at roof level posed a constant threat to the lift. This required ongoing monitoring to ensure a safe window of opportunity.
The Solution
In its entirety, the Generator had a combined weight of 18.0te. Our in-house team developed a comprehensive scheme to break down the generator into its individual components comprising of an Alternator (7.00te), Engine Block (7.00te), Radiator (2.00te), and a Base Frame (2.00te) before moving each item out on to the roof, and then being lifted to the ground some 87m below.
Plant handling solution and full contract lift planning, covering lift logistics, traffic management, RAMS, and coordination — enabling the Generator to be safely and efficiently installed into place.
The project demonstrated:
• Expert lift planning and execution
• Real-time risk assessment and decision-making
• Seamless coordination across teams
• Commitment to health & safety at every level
✅ Lift completed safely with zero incidents
✅ All Components installed on schedule
✅ Positive feedback from client and site stakeholders
Conclusion
This project showcases the importance of proactive planning, adaptable operations, and a strong safety-first culture. By putting people and process before pressure, the team once again delivered a successful plant installation under challenging conditions.
Need Help With a Complex Lift?
From complex multi-tonne lifts in busy urban environments to challenging plant installations in confined spaces, we deliver with precision, safety & efficiency.
📞 Call us on 01604 622865
Radius Group are a dedicated team of experienced site specialists backed by an industry-leading technical department. We offer a comprehensive ‘turnkey’ service, from initial consultation to project completion.
For the 18.0te generator project, the team developed a scheme to break it down into individual components like the Alternator, Engine Block, Radiator, and Base Frame. This allowed each part to be moved onto the roof and then safely lifted 87m to the ground, overcoming challenges like tight access and significant height.
The planning for the generator project included a comprehensive plant handling solution and full contract lift planning. This covered lift logistics, traffic management, RAMS (Risk Assessment and Method Statements), and coordination to ensure safe and efficient installation.
The project involved real-time risk assessment and continuous monitoring of conditions, such as high winds at roof level. This allowed the team to identify and utilize safe windows of opportunity for lifting, demonstrating a commitment to health and safety at every level.
Yes, the project detailed on the page involved both the specialist removal and subsequent reinstallation of an 18.0te backup generator. The generator was removed from the 17th floor, refurbished, and then reinstalled by the team.