Projects – 'Office Development'

9-Storey Building Crane Project: First Street, Manchester

What equipment was used for the project?

The equipment used for the project was a Potain MR608.

What was the project location?

Plot 9a First Street, Manchester

What was the project operation?

The project operation was an Office Development.

Background

Supporting the construction of a 9 storey building, which will have a BREEAM minimum rating of Excellent and is also one of the first offices in Manchester capable of achieving a minimum NABERS Design for Performance rating of 5.5* stars or above – the highest level of environmental performance in use.

For project info click here.

Overview

BAM were appointed for the delivery of the next phase of office development at First Street in Manchester City Centre.  Radius erected a Potain MR608 top-slewing crane on site in May 2023, with a planned duration of 42 weeks. The MR608 is perfect for power plants or high-rise buildings including super-tall structures. It is designed for a quick setup and faster working speeds.

To find out more about our Tower Crane Hire click here

“

“Just wanted reiterate our thanks to you and your team for their brilliant work on site delivering the project on time, look forward to working with you in the future.”

Justin JohnsonBrush Transformers

How does Radius Group make a difference in lifting solutions?

Radius Group are a dedicated team of experienced site specialists backed by an industry-leading technical department. We offer a comprehensive ‘turnkey’ service, from initial consultation to project completion.