Radius have assembled, lifted and positioned 3no bridge beam pairs from their trestles to final location as part of the new Bedford bypass project for MPB using a 1000te crane. The bridge beams pairs varied in weight from 85te per pair for the central beams to 105te per pair for the outside beams.

Crane: LTM1800 (LTM11000DS) supplied by Baldwins Crane Hire.

Other Equipment: Modulift Spreader Beam (MOD110), Wire Rope Slings and bow shackles.

Frequently Asked Questions

1 What services did Radius Group provide for the New Bedford Bypass project?

Radius Group was responsible for the critical heavy lifting operations on the New Bedford Bypass project. Their services included the assembly, lifting, and precise positioning of three bridge beam pairs from their trestles to their final locations.

2 What type of equipment and lifting capacity did Radius Group employ for this project?

For the New Bedford Bypass project, Radius Group utilized a 1000-tonne crane (LTM1800/LTM11000DS) from Baldwins Crane Hire. They also employed specialized equipment like a Modulift Spreader Beam, wire rope slings, and bow shackles to handle bridge beam pairs weighing between 85 and 105 tonnes.

3 Who was the client for the New Bedford Bypass lifting operations?

Radius Group provided their specialized lifting services for MPB as part of the new Bedford Bypass project. This demonstrates their capability to partner with major contractors on significant infrastructure developments.